Concrete Slab Prep Checklist

Everything that matters before the concrete shows up.

The checklist

  1. Confirm the dig. Excavate to firm, undisturbed soil. If you hit soft spots, dig them out and backfill with compacted stone — concrete poured over mush will settle and crack.
  2. Base: 4–6 inches of compacted crushed stone. Compact in 2–3 inch lifts with a plate compactor or hand tamper. This is the single highest-leverage step; most cracked slabs trace back to a lazy base.
  3. Forms: level, staked, braced. Set finished height with a string line and level — you can't fix a slope after the pour. Oil or form-release the inside faces so forms strip cleanly.
  4. Reinforcement in place. Rebar or welded wire mesh, chaired up so it sits in the middle of the slab — steel lying on the dirt does nothing. Overlap bars 12 inches, tie intersections.
  5. Drainage slope: 1/8 to 1/4 inch per foot away from the house. Water pooling against a foundation is a slow-motion disaster.
  6. Control joints planned. Cut or tooled joints every 8–12 feet (rule of thumb: joint spacing ≈ 2–3× slab thickness in feet for a 4″ slab). Concrete cracks — joints decide where.
  7. Order 5–10% extra (run the concrete calculator first) and have the truck's number saved. Coming up short is the one mistake you can't undo.
  8. Cure it. Keep it damp for at least 3–7 days — misting, wet burlap, or curing compound. Concrete that dries out in the first 48 hours never reaches its design strength.

Mistakes that crack slabs

FAQ

Do I need rebar in a concrete slab?
For most residential slabs, yes — #3 or #4 rebar on 18″ centers, or welded wire mesh at minimum. Steel in the middle of the slab controls cracking; steel on the dirt does nothing.
How thick should the gravel base be?
4–6 inches of compacted crushed stone. Compact it in lifts — dumping six inches loose and tamping the top only compacts the top.

Worked example: a 12 by 20 ft patio slab

Here is the prep for one common job, a 12 by 20 ft (240 sq ft) patio slab, 4 inches thick, worked out with the same figures the calculators on this site use:

ItemMathYou need
ExcavationDig out slab thickness (4 in) plus base (5 in) plus sodAbout 10 in deep over 240 sq ft, roughly 7 cu yd of spoil
Gravel base240 sq ft at 5 in deep = 100 cu ft = 3.7 cu yd; crushed stone at 1.4 tons per cu ydAbout 5.2 tons, roughly $182 at $35 per ton
Concrete240 sq ft at 4 in = 80 cu ft = 2.96 cu yd, plus 5 to 10% overageOrder 3.25 cu yd ready-mix, or about 134 eighty-lb bags at 0.6 cu ft per bag
Rebar#4 bar on 18 in centers, both directions: 9 bars of 20 ft plus 14 bars of 12 ftAbout 348 linear ft, roughly 18 twenty-ft sticks, plus chairs and tie wire
Control jointsPanels no larger than about 10 ft in either directionOne joint each way, dividing the slab into four 6 by 10 ft panels

The bag number is the quiet lesson there. Past about one cubic yard, hand mixing stops being frugal and starts being a workout with a deadline. The truck costs more per yard and saves the pour.

The day-before sequence

  1. Walk the forms. Check diagonals for square, confirm the finished height against the string line, and kick every stake. Forms that move during the pour do not move back.
  2. Confirm the steel is chaired. Rebar should sit mid-slab on chairs or dobies, tied at the laps. If it is lying on the stone, fix it now, not after the truck arrives.
  3. Dampen the base. Moist, not puddled: a damp base keeps the ground from pulling water out of the fresh concrete.
  4. Stage the tools. Screed, bull float, edger, jointer, broom, and curing supplies within reach. Concrete does not wait for a store run.
  5. Check the weather twice. A hard freeze in the first 24 hours or a downpour during finishing can ruin the surface. Postponing a pour is annoying; tearing one out is worse.
  6. Confirm the truck and the crew. Reconfirm the delivery window, the slump you ordered, and that every helper knows their job before the drum starts turning.

Mistakes that happen off the slab